Big Sun Solar’s 2.6 megawatt solar project for automotive supplier Vitesco Technologies is complete seven months after its first announcement.
Along with being the largest single-location project San Antonio-based Big Sun has ever commissioned, what makes the project unique, says CEO Robert Miggins, was that it formed under a historic three-party agreement between Vitesco, Big Sun and Guadalupe Valley Electric Cooperative.
“To our knowledge, it’s the first three-party PPA that we know of in Texas,” he said.
The project, which consists of 4,800 ground-mounted solar panels on a 12-acre solar farm next to Vitesco’s Seguin manufacturing facility, is fully operational after five months of construction, Miggins said. Generating 4,800 megawatt hours per year – enough energy to power 330 Texas homes – the project will account for about 13% of Vitesco’s annual energy consumption at its Seguin facility and reduce emissions equivalent to removing nearly 600 cars from the road for a year, according to Big Sun.
San Antonio Business Journal